Cardiovascular Institute at Glenbrook Hospital – Progress Update
December 2023 Progress and Activities
Completed:
Pfingsten Lobby Turnover
Mechanical & Plumbing Install in Basement
UCU & PACU Headwall Installation
Cath & EP Drywall & Painting
EP & Hybrid OR Flooring
CVICU Headwall Install
CVICU Flooring
CVICU Tile Install
Generator Install & Start-UP
OH OR & Hybrid OR Boom Install
Hybrid OR Siemens Technology Install
Ongoing:
Patient Transport Elevator Installation
Electrical Install in Basement
CT Installation Project on 4 North
UCU & PACU Flooring Installation
CVI Lobby Terrazzo Install
CVI Lobby Feature Wall Install
UCU Sliding Door Install
UCU Millwork Install
Cath Lab Flooring
Plumbing Fixture Installation
Ceiling Install
Lighting Install
Air Handler Start-Up
EP Lab Boom Install
EP Lab Siemens Technology Install
Procedural Area Millwork Install
CVICU Sliding Door Install
CVICU Millwork Install
CVI Admin Office Flooring
Upcoming Activities:
Cath Lab Siemens Technology Install
Automatic Transfer Switch Delivery & Installation
Exterior Building Sign Install
Monument Sign Modifications
CVI Admin Office Glass Wall Install