Cardiovascular Institute at Glenbrook Hospital – Progress Update
October 2023 Progress and Activities
Hoping everyone had a great October. We are excited to bring you updates for the CVI Expansion at Glenbrook
Completed:
Pfingsten Lobby Terrazzo Install
Pfingsten Lobby Drywall and Paint
Blue Parking Lot Paving
Exterior Canopy Steel Shell
Open Heart OR Drywall & Painting
Open Heart OR Flooring
Hybrid OR Drywall & Painting
Mechanical, Electrical & Plumbing Install in Phases IV & V
SPD Cart Washer Install
CVICU Drywall Install
Ongoing:
Patient Transport Elevator Installation
Mechanical, Electrical & Plumbing Install in Basement
CT Installation Project on 4 North
UCU & PACU Flooring Installation
UCU & PACU Headwall Installation
CVI Lobby Terrazzo Install
UCU Sliding Door Installation
Cath & EP Drywall & Painting
Cath, EP & Hybrid OR Flooring
Plumbing Fixture Installation
Ceiling Install
Lighting Install
CVICU Headwall Install
CVICU Flooring
Upcoming:
Pfingsten Lobby Furniture & IT Install
CVI Lobby Feature Wall Install
OH OR, Hybrid OR and EP Lab Boom Install
Hybrid OR and EP Lab Siemens Technology Install
Air Handler Start-Up
Generator Delivery & Start Up
Automatic Transfer Switch Delivery & Installation