August 2023 Progress and Activities

 

As summer draws to a close, we are excited to bring you construction updates from our Cardiovascular Institute at Glenbrook Hospital expansion

 

Completed:

Glass Install at Future Pfingsten Lobby
Roofing Material Install
2nd Floor Office Wall Framing
Restroom & Locker Room Tile Install
Door Frame Install

Ongoing:

Exterior Canopy Steel Shell
CVICU Wall Construction
Lobby Steel Fireproofing
Door Frame Install
Restroom & Locker Room Tile Install
Mechanical, Electrical & Plumbing Install in Basement
CVICU Phase II – Demolition
Passenger Elevator Installation

Upcoming:

Passenger Elevator Install
CT Installation Project on 4 North
UCU Sliding Door Installation
UCU & PACU Flooring Installation
UCU & PACU Headwall Installation
Procedural Area Drywall & Painting