April 2023 Progress and Activities

 

Happy Spring! We’re excited to bring you monthly updates as we make progress on our expanded Cardiovascular Institute

 

Completed:

Pfingsten Entrance Demolition
Phase IV Concrete Pour
Steel Cribbing Installed on the Roof

Ongoing:

Pre-Cast Installation
Mechanical, Electrical & Plumbing Install in Phases I-IV
Framing Layout and Install in Phases I-IV
Phase V Concrete Pour
Structural Footings for the Future Lobby

Upcoming:

Exterior Glazing Install
Exterior Canopy Steel Shell
Cooling Tower Crane Picks