November 2022 Progress and Activities

 

Completed:
Temporary Entrance Concrete
Physicians Lot Modifications
Phase I Concrete Pour
Light poles, signage, and final landscaping construction at the new East Parking Lot

 

Ongoing:
Concrete Footings for Phave IV
Phase II Concrete Pour
Above Ceiling Rough-In at Phase I

Upcoming:
Nicor Gas line Installation
Phase III, IV and V Concrete