Information

  • Remodeling a 11,000 square foot empty warehouse into a fully functional operating surgery center with complete recovery capabilities.
  • Using only the existing base structure, all utilities were replaced:
    • emergency power generation
    • air-conditioning
  • Project Cost: $4 million Project Duration: 6 months

Outcomes

  • Extensive site work was needed to provide parking and infrastructure
  • Purchase and relocation of furniture and equipment coordination were essential components in achieving the schedule and assuring surgical cases were not delayed for the client

Team

Architect – CFP Group

Contractor – WB Olson

Mechanical/ Electrical Engineer – NorthStar Engineering